Construction Update: Hamilton Walton Transformation Phase II

 

Bldg B level 2 deck with Bldg C and Hayward field in the background

 

Phase 2 of the UO Hamilton Walton Transformation is in full swing. Fortis Construction is preparing to pour the remaining portions of post-tensioned deck at Building B and currently framing the third floor of Building C.

 

Crews preparing the Bldg B level 2 deck for concrete

 

Building B will be a six-story building that contains academic spaces, a service center, a package locker delivery center, and residences for 705 students. Building C will be a five-story building that contains a mix of four-bedroom apartments and single-occupant “micro” efficiency units for 400 students.

 
 

Buildings B and C are on track to being LEED Gold. They will be ready for occupancy by July 2023.

 

Phase I: Building A. Phase II: Buildings B and C. Phase III: Development of a New Green Space.