1203 Willamette Construction Sequences
Steps in the Sequence:
1. Existing 2017 Facade
2. Existing Facade Stripped Back to Reveal Original Structure
3. Existing Columns Reinforced and New Columns Inserted
4. Glulam and Concrete Shear Wall Inserted; Weather Barrier Going in Place
5. Windows, Garage Doors, and Cladding Installed
6. Finished 2018 Facade
Steps in the Sequence:
1. Existing 2017 Interior with Metal Window Grating Removed
2. Existing Wall Stripped Back to Reveal Original Structure
3. New Columns Inserted
4. Gypcrete Floor Installed
5. Sprinklers Installed
6. Finished 2018 Interior - Rowell Brokaw's Office